Customer:
Line Creek Resources Ltd.
(now Luscar Ltd. – Line Creek Mine)
Description: Horseshoe
Ridge Project - Phase I and II
Location: Sparwood,
BC
1996 and
1997
This $8 million project
involved the construction of a haul road and the development of
a pit, including a full drill and blast program. We employed the
rarely seen "Cast Blast" technique on this project to
reduce the volume of material to be hauled. A 245 Excavator, D10N
track-type Tractor and four 773 CAT Trucks were the major pieces
of equipment working on this project.