Customer:
City of Kimberley
Description: Mark
Creek Supply Main
Installation of welded steel supply main and supply of duck-tile
iron distribution main.
Location: Kimberley,
BC
1995
A unique challenge,
this project involved laying 4km of pipe in the solid rock creek
bed of the narrow Mark Canyon. As Mark Creek is the source of Kimberley’s
drinking water, innovative hammer techniques were used to avoid
using blasting powder which might have contaminated the water supply.
This was a three phase project which involved logging,
stripping and grubbing, pioneering and finally laying pipe.